Since the last post I've gotten a number of things done.
I got both the front door & the sliding door openings taped.
 |
Front Door edges taped
|
 |
Sliding Door edges taped
|
I also installed the breaker box in the house and all of the electrical boxes for outlets, switches, lights & smoke detectors. The ones on the outside of the house have a piece of stained 3/4" pressure treated plywood that they're mounted on.
 |
Breaker Box
|
 |
Plywood mounting block
|
On that mounting block in the photo above the meter box is mounted and connected to the breaker box.
 |
Meter Box
|
 |
Breaker Box connected
|
I also installed the roof edge trim on the east & west gable ends.
 |
East Trim
|
 |
West Trim
|
Next step is to install the trim on the north & south eaves, get it stained and then install drip edge on all four sides. After that I'll be ready for roofing.