Yesterday afternoon I got a call from the septic folks and they had a break in their schedule and wanted to install the septic system today. So they got started this morning, should have it done by end of day and they plan to be back early next week to do the final fill and grading.
Friday, November 4, 2022
Subscribe to:
Post Comments (Atom)
Lots of progress
Since the last post I've gotten a lot done. Finished the spackling and painting and painted the inside of the front door. I picked up a...
-
During the past few days I put up and stained the soffit under the gable ends, and the soffit & soffit vent under the eaves. Today I st...
-
Yesterday I finished installing the sheetrock. Today I started the process of mud and tape. I've never been very good at this, or more...
-
When I picked up my order of roofing panels a couple of them were damaged so I had to return them and re-order. Today I installed the last...